Loft Conversion Process

 
1. Scaffolding is erected a day or two before commencement of works. 2. Loft team arrive and receive delivery of materials.   3. First stage is construction of floor.  
4. Once floor is down customer can view loft area to make any final layout changes. 5. Stairs are ordered and we continue with internal construction, if a dormer is required it is built weather permitting and Velux windows are fitted. 6. Insulation is started and the first fix plumbing and electrical specification is commenced-customer is invited to finalise positions for lights and sockets.
7. Shaft is cut ready for stairs and stairs arrive following day and fitted on same day. 8. Insulation finalized and building inspector arrives for his inspections. 9. Plasterboards are fitted and loft teams work is coming to an end.
10. Plasterers arrive and spend 2-4 days. 11. Following week the electrician second fixes followed by plumber and carpenter who snags to reach a final completion. 12. Building inspector passes final completion.

 

Copyright Touchstone Lofts | Contact Us